ROADMAP
OUR STRATEGY AND PROJECT PLAN
Planning & Permits (~1–2 Months)
- Initial Design & Budgeting
Create preliminary designs, establish budgets, and set overall project scope. - Permits & Approvals
Submit applications for building permits and other required local/government approvals.
Site Preparation (~1–2 Months)
- Clearing & Grading (1–2 weeks)
Remove existing vegetation, debris, and level the ground. - Excavation & Foundation (2–4 weeks)
- Soil Testing – Ensure ground stability and identify any special foundation needs.
- Foundation Work – Pour footings, slabs, or other foundation elements.
Superstructure Construction (~3–6 Months)
- Framing (4–8 weeks)
Erect walls, floors, and roof framing. - Roofing (2–4 weeks)
Install roof trusses and covering (shingles, metal, tiles, etc.). - Exterior Finishes (4–6 weeks)
Apply siding, brickwork, stucco, or other exterior cladding.
MEP Installation (~2–4 Months)
- Plumbing (3–6 weeks)
Run water supply lines, drains, and install fixtures. - Electrical (3–6 weeks)
Wire the structure for power, lighting, and other electrical services. - HVAC (3–6 weeks)
Install heating, ventilation, and air conditioning systems.
Interior Finishes (~3–5 Months)
- Insulation & Drywall (4–6 weeks)
Ensure proper insulation, then hang and finish drywall. - Flooring (2–4 weeks)
Install tile, hardwood, laminate, or other flooring materials. - Painting (2–4 weeks)
Prime and paint walls, ceilings, and trims. - Cabinetry & Fixtures (3–5 weeks)
Fit kitchen cabinets, bathrooms, built‐in storage, and final fixtures.
Final Touches & Landscaping (~1–2 Months)
- Final Inspections (1–2 weeks)
Schedule official building, electrical, plumbing, and safety inspections. - Punch List & Corrections (2–4 weeks)
Identify and fix any remaining defects, incomplete tasks, or cosmetic issues. - Landscaping & Exterior Work(2–4 weeks)
Grade, plant, and add walkways, patios, or other finishing touches to the exterior.